Common mistakes in bill of quantities
A bill of quantities (sometimes referred to as 'BoQ' or 'BQ') is a document prepared by a cost consultant (often a quantity surveyor) that provides project-specific measured quantities of the items identified by the drawings and specifications in the tender documentation for construction works.
It is very important that bills of quantities are prepared according to a standard, widely recognised methodology. This helps avoid any ambiguities or misunderstandings and so helps avoid disputes arising through different interpretations of what has been priced.
However, there are some common mistakes that can be made in the bill of quantities. These include:
- Inaccurate measurement of quantities.
- The inclusion of irrelevant preliminary items (this can be due to using preliminary items from a previous project which, although it may be similar, contains differences in scope).
- Insufficient information given in the descriptions.
- Omissions and discrepancies between the BoQ and the drawings or specifications (perhaps due to out-of-date or inaccurate information being used).
- Omissions or double-counting of items (this can be due to more than one quantity surveyor working on the same bill).
- Omission of temporary works items.
There can also be errors made in the pricing, such as:
- Incorrect understanding of the work method.
- Past performance used to assume future productivity.
- Inexperience of the estimator.
- Ignoring the relationship between items of work.
- Changes that are made late in the process.
- Inaccurate assumptions regarding items in the BoQ.
- Arithmetic errors.
- Differences in currencies not considered.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities software.
- Common mistakes in construction tenders.
- Cost plans.
- Cost overruns.
- Elemental bill of quantities.
- Estimate.
- How to take off construction works.
- Measurement.
- Taking off.
- Types of bill of quantities.
Featured articles and news
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.