Common mistakes in bill of quantities
A bill of quantities (sometimes referred to as 'BoQ' or 'BQ') is a document prepared by a cost consultant (often a quantity surveyor) that provides project-specific measured quantities of the items identified by the drawings and specifications in the tender documentation for construction works.
It is very important that bills of quantities are prepared according to a standard, widely recognised methodology. This helps avoid any ambiguities or misunderstandings and so helps avoid disputes arising through different interpretations of what has been priced.
However, there are some common mistakes that can be made in the bill of quantities. These include:
- Inaccurate measurement of quantities.
- The inclusion of irrelevant preliminary items (this can be due to using preliminary items from a previous project which, although it may be similar, contains differences in scope).
- Insufficient information given in the descriptions.
- Omissions and discrepancies between the BoQ and the drawings or specifications (perhaps due to out-of-date or inaccurate information being used).
- Omissions or double-counting of items (this can be due to more than one quantity surveyor working on the same bill).
- Omission of temporary works items.
There can also be errors made in the pricing, such as:
- Incorrect understanding of the work method.
- Past performance used to assume future productivity.
- Inexperience of the estimator.
- Ignoring the relationship between items of work.
- Changes that are made late in the process.
- Inaccurate assumptions regarding items in the BoQ.
- Arithmetic errors.
- Differences in currencies not considered.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities software.
- Common mistakes in construction tenders.
- Cost plans.
- Cost overruns.
- Elemental bill of quantities.
- Estimate.
- How to take off construction works.
- Measurement.
- Taking off.
- Types of bill of quantities.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
ECA calls for an exemption for contractors working away from home.
Fire performance of thermal insulation
Flat roof assemblies with PV.
Become a Professional Development Partner
CIOB launches a new framework for staff development and chartered membership.
Dorset's first conservation campaigner?
Gov.uk - Hot-rolled steel plate
New anti-dumping measure imposed on South Korea.
ECA responds to the Milburn Report
Youth employment to be linked to workforce demand.
The construction industry urgently needs to attract new talent
CIOB responds to Neets report.
Grenfell Tower community update
Memorial columns to be retained as careful dismantling continues.
When buildings reflected the local resources available.
CIOB reports 57% are using artificial intelligence technologies.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.